Clothing Production Calendar 2027: When to Order From a Bangladesh Factory

A 2027 calendar strip from January to December. Chinese New Year is marked from 5 to 13 February, Bangladesh's Eid-ul-Fitr factory closure at about 6 to 15 March and Eid-ul-Azha at about 13 to 21 May, and the monsoon from June to September. A worked example below: for stock on sale from 1 September, confirm the order by 18 June by air, or by 11 May by sea to the UK or EU.

To have clothing from Bangladesh on sale on a given day in 2027, confirm the order about 75 days before it by air, or about 102 days before it by sea to the UK or Europe, 107 to the US or Canada and 109 to Australia. Add about 10 days if the work falls across either Eid, when Bangladesh's garment factories close: Eid-ul-Fitr is expected on 10 March 2027 and Eid-ul-Azha on 17 May 2027. So a range going on sale on 1 June 2027 needs confirming by about 23 February by air, or 9 February by sea to the UK.

Collective Studio Ltd is a family-run knitwear factory in Narayanganj, Bangladesh, that cuts and sews T-shirts, hoodies, joggers and activewear for brands in the UK, Europe, the USA, Canada and Australia, from 150 pieces per style and per colour. The dates below are worked out with the same rules as our launch date calculator, which gives the exact count for any other day. Public holidays come from Bangladesh's 2027 list as reported in the national press; factory closures are our planning estimate and are confirmed for your order when we quote. Last verified: 28 November 2026.

The short version

  • By air: about 75 days from confirmed order to on-sale day, for any of our markets; we usually say about 70 days from order to door.
  • By sea: about 102 days to the UK or EU, 107 to the US or Canada, 109 to Australia.
  • Eid: two factory closures of about a week to ten days, around 10 March and 17 May 2027. Any order whose work crosses one needs confirming about 10 days earlier.
  • Chinese New Year: 6 February 2027. Trims bought from China stop for two to three weeks, so they should reach the factory by late January for anything sewn in February or March.
  • Sea freight from May to September meets the monsoon and the busy season at Chittagong; leave more slack, or fly part of the order.
  • Already late: a 1 March launch is now only possible by air, and the tech pack has to be complete by mid December 2026.

When to order for each 2027 launch

Each date is the last day to confirm the order, with a complete tech pack, for stock to be in your hands with a week to spare before the launch day. A star means the work crosses an Eid closure, and the date already allows for it.

On sale fromConfirm by, air (any market)Confirm by, sea to UK or EUConfirm by, sea to US or CanadaConfirm by, sea to Australia
Spring drop, 1 FebruaryPassedPassedPassedPassed
Spring, 1 March15 December 2026PassedPassedPassed
Easter and spring, 1 April5 January *18 December 202615 December 202611 December 2026
Summer drop, 1 May5 February *8 January *1 January *1 January *
Summer, 1 June (Australian winter)23 February *9 February *2 February *2 February *
1 July6 April *2 March *23 February *23 February *
Autumn and back to school, 1 August7 May *9 April *6 April *2 April *
Autumn, 1 September (Australian spring)18 June11 May *7 May *4 May *
Winter, 1 October16 July21 June15 June14 June
Christmas gifting, 1 November17 August20 July16 July13 July
Black Friday, 26 November10 September16 August10 August9 August
1 December (Australian summer)17 September20 August16 August13 August
Counted back from the on-sale day: a 7-day buffer to receive and list stock, freight at the slow end of what we have seen (8 days by air, 35 by sea to the UK or EU, 40 to the US or Canada, 42 to Australia), 5 days to pack and hand over, 45 days of production and quality control after sample approval, and one 10-day sampling round. A date that falls on a Saturday or Sunday moves to the Friday before. * The work crosses an expected Eid closure (6 to 15 March or 13 to 21 May 2027), so the date is earlier by the length of that closure. Each extra sample round adds about 10 days. Worked out on 28 November 2026; “Passed” means that date has gone.

For a launch day not in the table, or for two sample rounds, the launch date calculator counts it for you. A split shipment, with part of the order flown for the launch and the rest sent by sea, is available to every market.

Bangladesh holidays that stop production in 2027

The Cabinet approved Bangladesh's 2027 public holiday list on 2 November 2026 and the government published it on 5 November, The Financial Express reported: 29 holidays, with five days for Eid-ul-Fitr and six for Eid-ul-Azha. Eid dates follow the moon and can move by a day. Garment factories do not follow the government list day for day: the Bangladesh Labour Act, section 118, gives every worker 13 paid festival holidays a year and leaves the dates to the employer, so most of them fall around the two Eids.

Date in 2027HolidayWhat it means for an order
About 6 to 15 MarchEid-ul-Fitr (expected on Wednesday 10 March; government holiday 8 to 12 March)The longest stop of the year. In March 2026 many factories declared up to 10 days off, with most closed from 18 to 27 March
About 13 to 21 MayEid-ul-Azha (expected on Monday 17 May; government holiday 15 to 20 May, with Buddha Purnima on 20 May)A second stop of about a week. In May 2026 Dhaka factories released workers in stages over four days before Eid
21 FebruaryInternational Mother Language DayA one-day holiday (a Sunday in 2027)
26 MarchIndependence DayFalls on a Friday, the usual weekly day off
14 AprilPohela Boishakh, the Bengali New YearA one-day holiday
1 MayMay DayFalls on a Saturday
9 and 10 OctoberDurga PujaTwo days
16 DecemberVictory DayA one-day holiday
25 DecemberChristmas DayFalls on a Saturday
Government dates from Prothom Alo's report of the 2027 list (5 November 2026). Factory closure ranges are our estimate from the 2026 pattern, reported by The Financial Express and UNB; BGMEA and BKMEA usually announce each Eid break a week or two before it. Other public holidays are single days.

Both Eids arrive about 11 days earlier each year: Eid-ul-Fitr was on 21 March in 2026 and is expected on 10 March in 2027. Our guide to how long clothing manufacturing takes explains each stage of the timeline the table is built on.

Our sewing floor in Narayanganj during a working shift. Over each Eid the floor stops for about a week, which is why the order dates above allow for it. Video page: Our sewing floor in Narayanganj

Chinese New Year and trims from China

Chinese New Year falls on Saturday 6 February 2027, and China's official holiday runs for nine days, from 5 to 13 February, the Beijing municipal government announced. Zips, labels, elastics and some yarns and speciality fabrics are bought from China, and suppliers there often stop for two to three weeks around the holiday and restart slowly. In 2027 Chinese New Year and Eid-ul-Fitr are only about four weeks apart, so any trim from China for a February or March production should reach the factory before late January. Plain cotton jersey, fleece and rib are knitted in Bangladesh and are not affected.

Sea freight from May to September

The monsoon runs from June to September, and UNCTAD describes recurring seasonal congestion at the Port of Chittagong from April to October, with ships sometimes waiting more than a week. Nobody publishes a forecast for 2027. For a sea shipment due to leave between May and September, add a week to the buffer, or fly the part of the order you need for launch day and send the rest by sea.

2027 season by season

  • Spring and summer 2027 (on sale March to May): by sea most of these dates have passed or fall in December 2026; by air, confirm by early January for an April launch. A May launch crosses Eid-ul-Fitr whichever way it ships.
  • Summer drops (on sale June and July): confirm between early February and early April. Sea shipments for July cross both Eids.
  • Autumn and winter 2027 (on sale August to October): confirm from April to July. An August or September launch by sea crosses Eid-ul-Azha in May.
  • Black Friday and Christmas 2027 (on sale November): confirm by mid to late July by sea, or between mid August and mid September by air. No Eid falls in this window in 2027, but allow for your own Christmas closing if stock must be listed before December.
  • Australia: winter starts on 1 June and summer on 1 December, so an Australian winter range is the June row and a summer range the December row.

Trade shows early in 2027

If you want to meet makers in person before you order, five shows fall before the spring order dates:

Dates as each organiser listed them in November 2026; check before you book travel.

Rule changes to plan around

Several import rules change during 2027, including who may be importer of record in the US from 5 January, the EU's new customs code from 21 September and its forced labour ban from 14 December. Our guide to what changes for clothing imports in 2027 lists every decided change by date.

A checklist before you confirm

  • Tech pack complete: measurements, fabric and weight, colours, trims and labels, so sampling can start the day you confirm. Our tech pack template covers each section.
  • Trims from China: ordered in time to arrive before Chinese New Year if the order is sewn in February or March.
  • Eid: ask the factory for its closure dates for your order as soon as BGMEA announces the break.
  • Your side: who signs off the sample, and how fast. Every day it waits is a day off the buffer.
  • Freight: air, sea or a split, and who is importer of record at your end.

Frequently asked questions

When should I order clothing for a 2027 launch?

Confirm the order about 75 days before the on-sale day by air, or about 102 days before it by sea to the UK or EU, 107 to the US or Canada and 109 to Australia. Add about 10 days if the work crosses either Eid. For example, a range on sale from 1 September 2027 needs confirming by about 18 June by air or 11 May by sea to the UK.

When are the Eid holidays in Bangladesh in 2027?

Eid-ul-Fitr is expected on Wednesday 10 March 2027, with a government holiday from 8 to 12 March, and Eid-ul-Azha on Monday 17 May 2027, with a government holiday from 15 to 20 May. Both depend on the moon and can move by a day. Garment factories usually close for longer: in 2026 many declared up to 10 days for Eid-ul-Fitr.

Do garment factories in Bangladesh close for Eid?

Yes. Bangladesh law gives every worker 13 paid festival holidays a year and leaves the dates to the employer, so factories spend most of them around the two Eids. Plan on about a week to ten days for each, around 6 to 15 March and 13 to 21 May 2027, and ask the factory for its own dates.

How does Chinese New Year 2027 affect clothing made in Bangladesh?

Chinese New Year is on 6 February 2027 and China's holiday runs from 5 to 13 February. Garments sewn in Bangladesh often use zips, labels or elastics from China, which stop moving for two to three weeks, so those trims should reach the factory before late January. Cotton jersey and fleece knitted in Bangladesh are not affected.

When should I order for Black Friday and Christmas 2027?

For stock on sale from 1 November 2027, confirm by about 17 August by air or about 20 July by sea to the UK or EU, 16 July to the US or Canada, and 13 July to Australia. For Black Friday on 26 November, the dates are about 10 September by air and 16 August by sea to the UK or EU.

How long does it take to make clothing in Bangladesh?

On our floor, about 10 days of sampling, then 40 to 50 days of production after the sample is approved, then freight: about 5 to 8 days by air, or about four to six weeks by sea. By air that is about 70 days from order to door.

Where this applies

The manufacturing pages this guide relates to, if you are costing a real run.

Free tools & guides for this

Sources & further reading

Cite this guide

For journalists, writers, researchers and students.

Quoting this guide? Please credit Collective Studio and link to this page.

Reference

Homaira Jashim, Collective Studio. "Clothing Production Calendar 2027: When to Order From a Bangladesh Factory." 28 November 2026. https://collectivestudioltd.com/journal/clothing-production-calendar

Writing about us? Our press kit has our facts, logos and photos, free to use with credit.